Greece-Cyprus electrical interconnection project to reach completion by the end of 2031
The Hellenic Electricity Distribution Network Operator (IPTO/ADMIE) has reported on the progress of the electrical interconnection project between Greece and Cyprus. The project, which will route through Crete, is scheduled for completion by the end of 2031. This infrastructure initiative has a total budget of €1.94 billion and is designated as a Project of Common Interest (PCI) by the European Union. The project aims to integrate energy markets in the Eastern Mediterranean and address the fact that Cyprus is currently the last EU member state to be electrically disconnected from the European transmission system.
Technical specifications and construction status
The interconnection will span 898 kilometers and provide a capacity of 1,000 MW. The cable route is technically demanding, involving sea depths of up to 3,000 meters in the Eastern Mediterranean. To manage these conditions, the French vessel Abeille Marengo is currently conducting seabed surveys for the project route. Officials said that 60% of the required maritime surveys have been completed so far.
Construction is already underway for several components. The contract for the cable section has been signed and is currently in the construction stage. Additionally, a preferred bidder has been selected for the construction of the converter stations. The physical infrastructure will include the construction of a new substation in Cyprus and the expansion of the existing Damasta substation in Crete.
Economic impact and future expansions
The project is expected to provide substantial economic advantages for consumers in the region. According to a study by Aristotle University of Thessaloniki, the interconnection is estimated to provide an annual benefit for consumers ranging between €123 million and €138 million. The impact on electricity prices varies by location. In Cyprus, wholesale electricity prices are expected to decrease by €21.5 per megawatt-hour, which represents a 19% reduction. Regarding the impact in Greece, the impact on electricity prices is expected to be minimal, ranging from a 0.2% decrease to a 0.1% increase.
The current project serves as a foundation for further regional integration. A second phase of the project involves a 310-kilometer interconnection between Cyprus and Israel. A feasibility study for the Cyprus-Israel interconnection has already been completed with positive results, suggesting further potential for energy connectivity in the Eastern Mediterranean.
Glossary
- Aristotle University of Thessaloniki — The Aristotle University of Thessaloniki is the largest university in Greece and the fifth oldest tertiary education institution in the country. It is located in the centre of Thessaloniki and was founded in 1925.
- Project of Common Interest (PCI) — A Project of Common Interest (PCI) is a designation given by the European Union to infrastructure initiatives. In the context of the article, it refers to the electrical interconnection project between Greece and Cyprus.
- Eastern Mediterranean — The Eastern Mediterranean is a geographic region where energy market integration is being addressed through infrastructure projects. It is also a location characterized by sea depths of up to 3,000 meters.
This article was written with AI assistance from multiple news reports and is reviewed by our editors under our editorial principles. Editorial Standards · Tips & Contact
Comments 0